Consider the following data for the activities concerning a project :

Name of activity Pre - operations Duration (days)
A - 2
B A 3
C A 4
D B,C 6
E - 2
F E 8

 

  1. Draw a network diagram for the above project.
  2. Find the minimum time for completion of the project.
  3. Describe the critical path.
  4. Find Float