Determine the optimal sequence oh jobs that minimizes the total elapsed time on machine M1,M2, M3 in the processing order of M1M2M3:

Jobs → J1 J2 J3 J4 J5 J6 J7
M1 3 8 7 4 9 8 7 Hours
M2 4 3 2 5 1 4 3 Hours
M3 6 7 5 11 5 6 12 Hours
Engineering Mathematics-3 2013