5 jobs are to be processed on machines M1 and M2 in the order M1M2, their processing times are given below :

Job M1 M2
J1 5 2
J2 1 6
J3 9 7
J4 3 8
J5 10 4

 

Determine:

  1. The Job sequence
  2. Total processing time
  3. The idle times for M1 and M2
Engineering Mathematics-3 2013