Complete the following MRP matrix for item X:

Item: X LLC:1

LT : 2 Let size : min 50

1       2       3         4      5            6 7        8      

   Gross Requirement

Scheduled receipts

Project on hand (10)

Net Requirement

Planned order receipts

planned order releases

20

30

50

50 50 60 90 40 60

 

In what perios orders be released and what should be the size of these orders ?

 

 

 

 

Operations Management 2011